Project Facts

From UTC Library

Jump to: navigation, search

 

University of Tennessee at Chattanooga
New Library Building Fact Summary
November 16, 2007
 
Project Funded:                  July 2007
 
Target Completion Date:      July 2011
 
Project Dollar Amount:         48 million
 
Estimated Gross Sq. Ft.:     180,000
 
Estimated Usable Sq. Ft.:    126,000 – 144,000
 
Site Location:                    Corner of Vine and Douglas, adjacent to Chamberlain Field
 
Project Architect:               Derthick, Henley & Wilkerson/Artech (Joint Venture)
 
Project Timeline:
 
          November 2007 to April 2008
                   Draft program statement and submit to architect.
 
          April 2008 to March 2009
Prepare design and construction documents
 
March 2009 to June 2009
Submit final documents to TN State Fire Marshal (2-6 months review time)
 
June 2009 to August 2009
          Bidding and contract award process
 
August 2009 to July 2011
Construction of new library
 
July 2011
Move in to new library building
 
 
Project Background:
 
  • The Lupton Library opened in 1974 with:
    • 4,574 enrolled student, now 9,553
    • 1,100 patron seats at opening, now 700
    • 170,000 volumes, now 1.7 million items
  • The current library is 116,000 gross square feet.
  • A renovation and expansion to the Library has been on the UTC Capital Project list since before 1990
  • In 2000 the Tennessee Higher Education Commission found the current library building deficient by 58,575 square feet
  • Student learning styles and habits have changed significantly since the current library was first opened
  • Information research and scholarly practices began to change in the mid-1990s
  • Web-based communication tools are only 4 to 5 years old